Mid_Town_East_-_with_labels.png
The area contractors are working in runs north of Main Street to Fifth Street NE and east of Collins Ave to Fourth Ave Ne.

Concrete Repairs Taking Place in Mid-Town East

Sept. 18, 2024 –Residents in the Mid-Town East area (north of Main Street to Fifth Street NE and east of Collins Ave to Fourth Ave NE) may notice contractors working in their area. Multiple sidewalk, driveway and ADA ramp locations within the Mid-Town East area suffered some level of concrete surface scaling over the last two years. A contractor is currently working to fix the issue. Residents are asked to stay off the repaired areas until the cones have been removed (expected in a few days).

In approximately 2 weeks, the repaired areas will be sprayed with a sealant.

This fix will be monitored until next year to ensure that the scaling has been addressed.  These repairs are being completed under a warranty the City has with the contractor and will not be an additional cost to the homeowners.

Please contact the Engineering Department with questions at 701-667-3225.